§ 9.2 Subcontracts or other agreements shall conform to the applicable payment provisions of this Agreement, and shall not be <br />awarded on the basis of cost plus a fee without the Owner’s prior written approval. If a subcontract is awarded on the basis of <br />cost plus a fee, the Construction Manager shall provide in the subcontract for the Owner to receive the same audit rights with <br />regard to the Subcontractor as the Owner receives with regard to the Construction Manager in Article 10. <br />ARTICLE10 ACCOUNTINGRECORDS <br />The Construction Manager shall keep full and detailed records and accounts related to the Cost of the Work, and exercise such <br />controls, as may be necessary for proper financial management under this Contract and to substantiate all costs incurred. The <br />accounting and control systems shall be satisfactory to the Owner. The Owner and the Owner’s auditors shall, during regular <br />business hours and upon reasonable notice, be afforded access to, and shall be permitted to audit and copy, the Construction <br />Manager’s records and accounts, including complete documentation supporting accounting entries, books, job cost reports, <br />correspondence, instructions, drawings, receipts, subcontracts, Subcontractor’s proposals, Subcontractor’s invoices, purchase <br />orders, vouchers, memoranda, and other data relating to this Contract. The Construction Manager shall preserve these records <br />for a period of six (6) years after final payment, or for such longer period as may be required by law. <br />ARTICLE11 PAYMENTS FOR CONSTRUCTIONPHASESERVICES <br />§ 11.1 ProgressPayments <br />§ 11.1.1 Based upon Applications for Payment submitted to the Architect by the Construction Manager, and Certificates for <br />Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum, to the <br />Construction Manager, as provided below and elsewhere in the Contract Documents. <br />§ 11.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, <br />or as follows: <br />N/A <br />§ 11.1.3 Provided that an Application for Payment is received by the Architect not later than the first (1st) day of a month, the <br />Owner shall make payment of theamounts certified to the Construction Manager not later than the fifth (5th) day of the <br />following month. If an Application for Payment is received by the Architect after the application date fixed above, payment of <br />the amount certified shall be made by the Owner not later than « thirty-five» ( « 35 » ) days after the Architect receives the <br />Application for Payment. <br />(Federal, state or local laws may require payment within a certain period of time.) <br />§ 11.1.4 With each Application for Payment, the Construction Manager shall submit payrolls, petty cash accounts, receipted invoices <br />or invoices with check vouchers attached, and any other evidence required by the Owner or Architect to demonstrate that payments <br />already made by the Construction Manager on account of the Cost of the Work equal or exceed progress payments already received <br />by the Construction Manager, plus payrolls for the period covered by the present Application for Payment, less that portion of the <br />progress payments attributable to the Construction Manager’s Fee. <br />§ 11.1.5 Each Application for Payment shall be based on the most recent schedule of values submitted by the Construction <br />Manager in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum <br />Price among: (1) the various portions of the Work; (2) any contingency for costs that are included in the Guaranteed <br />Maximum Price but not otherwise allocated to another line item or included in a Change Order; and (3) the Construction <br />Manager’s Fee. <br />§ 11.1.5.1 The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the <br />Architect may require. The schedule of values shall be used as a basis for reviewing the Construction Manager’s Applications <br />for Payment. <br />§ 11.1.5.2 The allocation of the Guaranteed Maximum Price under this Section 11.1.5 shall not constitute a separate guaranteed <br />maximum price for the Cost of the Work of each individual line item in the schedule of values. <br />§ 11.1.5.3 When the Construction Manager allocates costs from a contingency to another line item in the schedule of values, <br />the Construction Manager shall submit supporting documentation to the Architect. <br />AIA Document A133 – 2019. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of <br />Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects.This draft was produced at 13:53:13 CDT <br />17 <br />on 08/18/2025 under Subscription No.20250116558 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance <br />® <br />with the AIA Contract DocumentsTerms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. <br />User Notes: (640e2aedf442e4498d096805) <br />Qbhf!259!pg!74: <br /> <br />