|
Contractor; and
<br />.2 assignment is subject to the prior rights of the surety, if any, obligated under bond relating to the Contract.
<br />When the Owner accepts the assignment of a subcontract agreement, the Owner assumes the Contractor’s rights and
<br />obligations under the subcontract.
<br />§5.4.2 Upon such assignment, if the Work has been suspended for more than 30 days, the Subcontractor’s compensation shall
<br />be equitably adjusted for increases in cost resulting from the suspension.
<br />§5.4.3 Upon assignment to the Owner under this Section5.4, the Owner may further assign the subcontract to a successor
<br />contractor or other entity. If the Owner assigns the subcontract to a successor contractor or other entity, the Owner shall
<br />nevertheless remain legally responsible for all of the successor contractor’s obligations under the subcontract.
<br />ARTICLE6 CONSTRUCTIONBYOWNERORBYSEPARATECONTRACTORS
<br />§6.1 Owner’s Right to Perform Construction and to Award Separate Contracts
<br />§6.1.1 The term “Separate Contractor(s)” shall mean other contractors retained by the Owner under separate agreements. The
<br />Owner reserves the right to perform construction or operations related to the Project with the Owner’s own forces, and with
<br />Separate Contractors retained under Conditions of the Contract substantially similar to those of this Contract, including those
<br />provisions of the Conditions of the Contract related to insurance and waiver of subrogation.
<br />§6.1.2 When separate contracts are awarded for different portions of the Project or other construction or operations on the site,
<br />the term “Contractor” in the Contract Documents in each case shall mean the Contractor who executes each separate Owner-
<br />Contractor Agreement.
<br />§6.1.3 The Owner shall provide for coordination of the activities of the Owner’s own forces and of each Separate Contractor
<br />with the Work of the Contractor, who shall cooperate with them. The Contractor shall participate with any Separate
<br />Contractors and the Owner in reviewing their construction schedules. The Contractor shall make any revisions to its
<br />construction schedule deemed necessary after a joint review and mutual agreement. The construction schedules shall then
<br />constitute the schedules to be used by the Contractor, Separate Contractors, and the Owner until subsequently revised.
<br />§6.1.4 Unless otherwise provided in the Contract Documents, when the Owner performs construction or operations related to
<br />the Project with the Owner’s own forces or with Separate Contractors, the Owner or its Separate Contractors shall have the
<br />same obligations and rights that the Contractor has under the Conditions of the Contract, including, without excluding others,
<br />those stated in Article 3, this Article 6, and Articles 10, 11, and 12.
<br />§6.2 Mutual Responsibility
<br />§6.2.1 The Contractor shall afford the Owner and Separate Contractors reasonable opportunity for introduction and storage of
<br />their materials and equipment and performance of their activities, and shall connect and coordinate the Contractor’s
<br />construction and operations with theirs as required by the Contract Documents.
<br />§6.2.2 If part of the Contractor’s Work depends for proper execution or results upon construction or operations by the Owner
<br />or a Separate Contractor, the Contractor shall, prior to proceeding with that portion of the Work, promptly notify the Architect
<br />of apparent discrepancies or defects in the construction or operations by the Owner or Separate Contractor that would render it
<br />unsuitable for proper execution and results of the Contractor’s Work. Failure of the Contractor to notify the Architect of
<br />apparent discrepancies or defects prior to proceeding with the Work shall constitute an acknowledgment that the Owner’s or
<br />Separate Contractor’s completed or partially completed construction is fit and proper to receive the Contractor’s Work. The
<br />Contractor shall not be responsible for discrepancies or defects in the construction or operations by the Owner or Separate
<br />Contractor that are not apparent.
<br />§6.2.3 The Contractor shall reimburse the Owner for costs the Owner incurs that are payable to a Separate Contractor because
<br />of the Contractor’s delays, improperly timed activities or defective construction. The Owner shall be responsible to the
<br />Contractor for costs the Contractor incurs because of a Separate Contractor’s delays, improperly timed activities, damage to
<br />the Work or defective construction.
<br />§6.2.4 The Contractor shall promptly remedy damage that the Contractor wrongfully causes to completed or partially
<br />completed construction or to property of the Owner or Separate Contractor as provided in Section10.2.5.
<br />AIA Document A201 –2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights
<br />reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents”are trademarks of The
<br />28
<br />American Institute of Architects.This draft was produced at 10:50:07 CDT on 08/19/2025 under Subscription No.20250116558 which expires on , is not for
<br />®
<br />resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract DocumentsTerms of Service. To report copyright
<br />violations, e-mail docinfo@aiacontracts.com.
<br />User Notes: (640e2aedf442e4498d0967fa)
<br />Qbhf!2:2!pg!74:
<br />
<br />
|