was uncovered in Central Park and Reservoir Woods Park on the southeast corner of Da1e and <br />Roselawn. This needed to be removed in order to construct the trail and amenities according to <br />plan. In order to save trees in Reservoir Woods Park, we constructed additional boulder retaining <br />walls. We added some limestone walls to the residential area along Dale Street to address <br />individual properiy owner concerns. The wa11 just north of Hwy 36 was added to the plan <br />because of a change in the grade on Dale Street during Mn�DOT's bridge reconstruction project. <br />We also had a few residents elect to ha�e their driveway reconstructed in conjunction with the <br />project. <br />Additional work added to this contract but not included in the original bid is; Reservoir Woods <br />parking lot at Alta Vista Drive- including a berm and landscaping pathway to dog park handicap <br />area (at Larpenteur), Central Park soccer field drainage correction, a vandal-proof coating on the <br />tunnel, and pathway signage. <br />Staff recommendation: All necessary items have been completed in accordance with project <br />plans and specifications. Since a11 items ha�e been completed as outlined in the policy regarding <br />final contract acceptance, staff recommends the City Council approve a resolution accepting the <br />work completed as 2000 Contract A and authorizing final payment of $213,732.06. The total <br />amount paid for 2000 Contract A is $1,823,819.38. <br />RECOMIV�NDED COUNCIL ACTION: <br />Approval of a resolution accepting the work completed as 2000 Contract A, starting the one-year <br />warranty and authorizing final payment of $2 13,73 2.06. <br />Prepared by: Debra Bloom <br />