Laserfiche WebLink
Page 2 of 2 <br /> <br />The project is approximately 17% complete with the reclamation area ready for paving the final <br />lift. Watermain in the Floral neighborhood is near completion, storm sewer installation and <br />grading is underway. Five percent is being withheld from the work completed in accordance <br />with the contract documents. The second payment is in the amount of $323,681.84. WSB has <br />provided a recommendation to pay the second voucher (Attachment C). Staff recommends that <br />Council approve Payment No. 2 (Attachment D). <br /> <br /> <br />Attachments <br /> <br />Attachment A: WSB Letter – Change Order No. 1 <br />Attachment B: Change Order No. 1 <br />Attachment C: WSB Letter – Payment No. 2 <br />Attachment D: Payment No. 2 <br />