<br /> I <br /> ... <br /> CHANGE ORDER NORTHERN TRAIL SEGMENT PAGE 2 41 <br /> Timelines I <br /> Should the City Council decide to approve this Change Order, the contractor could possibly <br /> finish both trail segments in 1996. However, because of a wetland area north of Arden Vista I <br /> Court, all construction within this area needs additional approval by the Rice Creek Watershed <br /> District. City Engineer, Greg Stonehouse, is looking into this issue and may have an update for <br /> the Council at the meeting on July 29, 1996. In the event that the City is not able to obtain a I <br /> second wetland permit in 1996, construction in the wetland area will have to wait until the spring <br /> of 1997. City Engineer Stonehouse will also confirm whether the contractor will extend their <br /> prices into 1997. I <br /> Recommendation <br /> I recommend the adoption of the following motion: "move to approve Change Order number one I <br /> to Thor Construction, Inc. for construction of the Northern Trail segment." <br /> I <br /> I <br /> 411 <br /> I <br /> I <br /> I <br /> I <br /> I <br /> I <br /> .1 <br /> I <br /> I <br />