<br />Owner: City of Centerville, 1880 Main Street, Centerville, MN 55038 Date July 2, 202C
<br />contractor: A-1 Excavating, 8237 State Highway 64/PO Box 90, Bloomer, WI 54724
<br />3ond Co: Merchants Bonding Co., 6700 Westown Pkwy., Bond No: MNC
<br />W. Des Moines, IA 50266 68604
<br />CHANGE ORDER NO. 1
<br />2020 DOWNTOWN AREA STREET AND UTILITY IMPROVEMENTS
<br />STANTEC PROJECT NO. 193804758
<br />Description of Work
<br />This Change Order provides for the following:
<br />Part A: Material and labor required to construct a temporary roadway during the unexpected project shutdown of
<br />approximately 8 weeks due to the COVID-19 virus.
<br />Part B: Additional storm sewer to accommodate future redevelopment and convey future runoff to the existing trunk
<br />line in CSAH 21 (Centerville Road).
<br />No.
<br />Item
<br />Unit
<br />Contract
<br />Quantity
<br />Unit
<br />Price
<br />Total
<br />Amount
<br />CHANGE ORDER NO. 1
<br />PART A: TEMPORARY ROAD
<br />1
<br />MOBILIZATION
<br />LS
<br />1
<br />$7,257.00
<br />$7,257.00
<br />2
<br />3" ROCK FOR TEMPORARY ROAD
<br />TN
<br />294.93
<br />$34.00
<br />$10,027.62
<br />3
<br />AGGREGATE BASE FOR TEMPORARY ROAD
<br />TN
<br />276.17
<br />$18,00
<br />$4,971.06
<br />TOTAL PART A: TEMPORARY ROAD
<br />$22,255.68
<br />PART B: STORM SEWER
<br />4
<br />12" PVC STORM SEWER
<br />LF
<br />22
<br />$63.00
<br />$1,386.00
<br />5
<br />15" PVC STORM SEWER
<br />LF
<br />-42
<br />$71.00
<br />($2,982.00)
<br />6
<br />12" RCP STORM SEWER, CLASS 5
<br />LF
<br />-29
<br />$56.00
<br />($1,624.00)
<br />7
<br />15" RCP STORM SEWER, CLASS 5
<br />LF
<br />-204
<br />$60.00
<br />($12,240.00)
<br />8
<br />18" RCP STORM SEWER, CLASS 5
<br />LF
<br />-400
<br />$64.00
<br />($25,600.00)
<br />9
<br />21" RCP STORM SEWER, CLASS 3
<br />LF
<br />159
<br />$76.00
<br />$12,084.00
<br />10
<br />24" RCP STORM SEWER, CLASS 3
<br />LF
<br />34
<br />$85.00
<br />$2,890.00
<br />11
<br />27" RCP STORM SEWER, CLASS 3
<br />LF
<br />342
<br />$94.00
<br />$32,148.00
<br />12
<br />30" RCP STORM SEWER, CLASS 3
<br />LF
<br />283
<br />$107.00
<br />$30,281.00
<br />13
<br />36" RCP STORM SEWER, CLASS 3
<br />LF
<br />21
<br />$147.00
<br />$3,087.00
<br />14
<br />4' DIA. STORM MANHOLE/CATCH BASIN MANHOI
<br />EA
<br />-4
<br />$3,350.00
<br />($13,400.00)
<br />15
<br />5' DIA. STORM MANHOLE/CATCH BASIN
<br />EA
<br />3
<br />$4,550.00
<br />$13,650.00
<br />MANHOLE
<br />16
<br />6' DIA. STORM MANHOLE/CATCH BASIN
<br />EA
<br />1
<br />$6,200.00
<br />$6,200.00
<br />MANHOLE
<br />17
<br />7' DIA. STORM MANHOLE/CATCH BASIN
<br />EA
<br />1
<br />$7,300.00
<br />$7,300.00
<br />MANHOLE
<br />18
<br />4' DIA. STORM CATCH BASIN MANHOLE WITH
<br />EA
<br />2
<br />$4,100.00
<br />$8,200.00
<br />SUMP
<br />19
<br />END SECTION FOR 12" HDPE PIPE
<br />EA
<br />1
<br />$300.00
<br />$300.00
<br />20
<br />CONNECT TO EXISTING STORM SEWER PIPE
<br />EA
<br />-4
<br />$800.00
<br />($3,200.00)
<br />TOTAL PART B: STORM SEWER
<br />$58,480.00
<br />CHANGE ORDER NO. 1 SUMMARY
<br />PART A: TEMPORARY ROAD
<br />PART B: STORM SEWER
<br />TOTAL CHANGE ORDER NO. 1
<br />$22,255.68
<br />$58,480.00
<br />$80,735.68
<br />193804758CHOl.xlsm