Timeline for Pheasant Marsh Phase 12`1 lots <br /> A. Start of Development Grading Construction <br /> May 2001 after road restrictions are lifter'. <br /> B. Start of Development Street and Utility Construction <br /> July 2001 after completion of grading, somewhat weather dependent. <br /> C. Finish of Development construction ready Model Home starts <br /> October 2001, somewhat weather dependent. <br /> D. Completion of Model Homes <br /> January- February 2002 Model Home Completion <br /> E. Home Sales begin for Pheasant Marsh Phase 1 <br /> February 2002, coordinated with Parade of Homes Spring Preview. <br /> F. Start of New Home Construction - Building permits <br /> March 2002 and beyond <br /> G. First completion of Phase I Pheasant Marsh Homes - <br /> Certiflcate of Occupancy <br /> May - June 2002 <br /> H. Opening of new Elementary School 1 Pheasant Marsh Phase I <br /> Enrollments <br /> September 2002 <br />