Identified Risk 11: The budget outlined in the document will not be adequate. <br />Solution / Strategy: See Knutson Identified Risk #3 for our VE process. <br />Identified Risk 12: � Weather delays <br />Our schedule accounts for the average expected amount of weather related <br />delays for this part of the country. If we experience an above average <br />Solution / Strategy: amount of weather related delays during construction, this will be added to <br />the weekly risk report and tracked for schedule and cost deviation. <br />Identified Risk 13: <br />Coordination with Parks and Recreation program activities to maintain <br />schedule. <br />See Owner ldentified Risk #4: During the clarification phase we will work <br />with the City to establish acceptable construction timeframes in which each <br />Solution / Strategy: <br />project site can be under construction. It will be critical that the start and <br />finish dates established for each site are adhered to by all parties involved. <br />If established dates change during construction this deviation will be added <br />to the weeklv risk report. <br />Identified Risk 14: <br />Solution / Strategy <br />Identified Risk 15 <br />Theft and/or vandalism. <br />See Owner ldentified Risk #3: We conduct pre-construction meetings with <br />our subs and vendors in which we discuss safety with regards to the job site <br />and public safety. We have a site specific safety plan that will be <br />distributed to all our subs and vendors. Jobsite perimeters will be clearly <br />defined/separated from the public. Tools and materials will be secured or <br />removed from every site on a daily basis. <br />Potential loss of trees in park due to construction damage. <br />Add specified tree protection will be provided and installed. Once on site, if <br />Solution / Strategy: � we feel there may need to be additional tree protection added we will <br />notify the project team immediately with any associated costs. <br />Identified Risk 16: I Excavation and site work. <br />We have coordinated the revised schedule with the City due to various <br />Solution / Strategy: scope changes. We are confident that we can complete the work as <br />currentiv scheduled. <br />Identified Risk 17: Keep projects at or below budget. <br />Solution / Strategy: See Knutson Identified Risk #3 <br />Risks 18 — 25 from the PBSRG list were generated by Knutson Construction <br />The schedule for each park that is listed in the specification is dependent on <br />the owner's allowance of scheduled public usage of each individual park. <br />Identified Risk 26: gased on many of the parks not being able to be shut down during the <br />summer months, a lot of work has to be completed in multiple locations <br />0 <br />