<br />2211 O’Neil Road, Hudson, WI 54016 t 651.256.3090
<br />www.b32eng.com
<br />B32 ENGINEERING GROUP, INC.
<br />We have reviewed the low bid information submitted by the Corval Group and requested,
<br />received and reviewed additional information in regards to the Quality Assurance requirements of
<br />Section 131811.1.02.A.1 that states the following.
<br />
<br />1. As evidence and assurance of the contractor’s ability to construct the project and support the
<br />Owner’s system with service the contractor installing and constructing the primary and
<br />secondary refrigeration systems must have successfully installed and constructed AMMONIA
<br />refrigeration systems for five (5) ice rink construction projects that are similar to this project
<br />and completed within the past five (5) years. Submit information on each project. Submittal
<br />shall be on company letterhead, signed by an authorized representative of the company and
<br />include project description, portion of project completed by the company, location,
<br />construction cost, completion date, owner's name, owner's representative, phone number
<br />and completion date of work.
<br />
<br />The Corval Group listed one ice rink project, constructed seven (7) years ago, where they stated a
<br />new compressor room and rink floor were installed for $196,726. They listed four (4) other ice
<br />rink facilities where they had maintenance and service contracts ranging in total value from
<br />$50,000 to $200,000 each for a 3-5 year period between 2017-2022. It was confirmed with the
<br />Corval Group that the work listed for these four (4) ice rink projects was maintenance and service
<br />type work and not new equipment installation. They provided information on other industrial
<br />grade ammonia projects completed in the last five (5) years that are not ice rink related projects.
<br />Based on the information that the Corval Group has provided, it does not meet the requirements
<br />or intent of Section 181811.1.02.A.1.
<br />
<br />We have also reviewed the bid information submitted by Total Mechanical Services, Inc. and find
<br />no irregularities that would cause us to be concerned with their bid. They have experience with
<br />this type of specialty work, and they are using experienced subconsultants.
<br />
<br />Bid Package 2 - Site
<br />The table below lists the four (4) lowest bids of the nine that were received. The engineer's
<br />estimate is also included based on the January 27, 2022 cost estimate presented to the City prior
<br />to the bid opening.
<br />
<br /> Engineer’s
<br />Estimate
<br />Goodmanson
<br />Construction
<br />Meisinger
<br />Construction
<br />Peterson
<br />Companies
<br />Kevitt
<br />Excavating
<br />Total Base $920,330 $914,450 $1,048,100 $1,093,899 $1,207,000
<br />Alt 1: Add’l run of drain tile $15,000 $20,000 $12,700 $18,485 $48,000
<br />Alt 2: Add’l 12” of select
<br />granular material under new
<br />pavement
<br />$14,400 $60,000 $39,700 $47,751 $56,000
<br />Alt 3: New ADA ramp w/ railing $88,000 $43,500 $76,200 $118,179 $160,000
<br />Alt 4: Delete two new concrete
<br />center islands with drains ($60,000) ($96,000) ($105,600) ($131,824) ($80,000)
<br />Alt 5: Concrete pavement and
<br />heating coil for new ADA ramp $5,000 $0 $2,500 $3,860 $29,000
<br />