Add to change the tracks for overhead doors #1141 C, E, F and #1140 E, G to form a standard <br />track to a high-lifttrack This change increased the overall height of the garage in these <br />areas. This change was called out in PR #5. Required to keep heat tubing high enough to <br />prevent damage from truck boxes. Add $565 <br />Deduct to remove one detector loop as directed in PR #11. Deduct $400 <br />Kellin�ton Construction Add $27,000 <br />Add for wood blocking at salt / sand storage building roof. This work was part of a proposal <br />request to complete the roofing at the salt / sand storage building. Add $2,389 <br />Furnish and install additional window blocking as indicated in ASI #5. Add $710 <br />Furnish and install a new tarp at the clearstory area of the e�sting Public Safety Building. <br />The e�sting taxp had numerous burn holes in it from the ironworkers. Also, install ice & <br />water membrane at the precast deck The existing membrane had been removed by the <br />ironworkers to anchor their beams. This item is a general conditions cost. Add $572 <br />Add to remove the roof edge, roof inembrane, built-up blocking, insulation and steel decking <br />at the South elevation of the existing North Public Works garage. This work was required to <br />tie the e�sting building into the new building but not indicated on the drawings. Add $4,987 <br />Add to remove the roof at the Public Safety entry area where the new building connects to the <br />e�sting building. This add also includes cutting in three (3) beam pockets into the concrete. <br />This work was required to tie into the existing building. Add $4,853 <br />Add for PR #5 Revision #3 to install the added bath accessories. Add $342 <br />Add to furnish and install additional wood blocking at detail9/A17.0 per PR #12. Add $908 <br />Add for the door hardware revision as called out in PR #14. Add $650 <br />Add for removing of an e�sting door and frame and the reinstallation of the new door, frame <br />and hardware per PR #17. Existing door not sound for future use. Add $978 <br />Add to have Kellington build temporary walls in the basement of the e�sting building where <br />the windows had to be removed. General condition item. Add $2,054 <br />Add to have Kellington build a temporary enclosure at the main entry doors. This enclosure <br />had to be moved and rebuilt for Harmon. This will be a backcharge to Harmon General <br />condition item. Add $312 <br />Add for numerous door and hardware changes relatingto doors 112A, 1130A, 1130B and <br />2241C as called out in PR 22, PR #22 Revision #1 and PR #22 Revision #2. These changes <br />are staff requested for operational functionality. Add $1,341 <br />Add for additional wood blocking at the bump-outs as shown on detail 10/A8.1 in PR #21 <br />Revision#l. Add $227 <br />